Question: We have a poured patio with two steps down from the door. We need to remove the top step in order to build a deck over the whole thing. It appears it was done in a single pour-we think we will probably need to board up the slider for protection and rent a jackhammer for the day. Anything we should consider before taking on this endeavor?
Answer: It is highly unusual that the steps and pad were done in one pour (but anything is possible). Usually the steps sit on the pad.
A couple of points - remember your neighbors - jackhammers can be heard for hundred's of yards. Get a dumpster to get rid of the concrete - safety - glasses, gloves, steel toed boots, there will most likely be rebar or wire mesh in the concrete, heavy duty bolt cutters are best to cut wire mesh, power saw with metal blade for rebar.
------------------------